Bryant Avenue North
Project Details
Project Type:
Resurfacing
Project Location:
Bryant Ave N
Construction Start Date:
May 2016
Asphalt mill and overlay work is scheduled to take place the week of June 15.
Duration of Construction:
3 weeks
Traffic Impact:
Traffic will be detoured.
Public Meetings:
Pre-Public Hearing:
6:30p.m., Tuesday, March 29
Creekview Recreation Center
5001 Humboldt Avenue North
Formal Public Hearing:
9:30a.m., Tuesday, April 5
Council Chambers, City Hall
350 South 5th Street, 3rd Floor
Project Updates
June 17, 2016: Project is complete.
May 26, 2016: The city curb and gutter replacement work is complete on the project.
Private utilities are still working on underground structures on the project when their work is complete the city can start resurfacing the street.
Asphalt mill and overlay work is scheduled to take place the week of June 15, 2016.
The city asphalt mill and overlay work is expected to take about 4 or 5 days to complete.
April 29, 2016: Private utilities have started work in the area ahead of the street resurfacing project.
Contact: Chris Trembath, 612-919-1196
(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.
Last updated Dec 20, 2016