Lyndale Ave S Resurfacing

Project Type:
This is a paving resurfacing project. Resurfacing projects use a mill and overlay process.  This process will consist of removing a portion of the existing asphalt pavement surface and placing a new surface over the entire street. The purpose of the resurfacing program is to extend the life of a roadway by approximately 10 years.  Without this program, streets in the in the program would not see surface improvements for many years.

Project Limits:
The resurfacing project is located in south Minneapolis on Lyndale Ave S from 56th St W to the newer pavement south of 61st S W.  This was originally paved in 1964 and the pavement is 49 years old.  58th St W from Trunk Highway 121 to Lyndale Ave S was originally paved in 1954 and is 59 years old.

Construction Start Date:
Phase 1: Lyndale Ave S from 58th St W to south of 61st St W is scheduled for October 7th-9th. The west two thirds will be resurfaced at this time, and the east third will be left open for northbound traffic and will be done in Phase 2.  Half of 58th St will also be done at this time.

Phase 2: Lyndale Ave S from 57th to 58th St and the east third between 58th and 61st will also be done along with half of 58th St from Lyndale Ave to TH121.  This is scheduled for October 14th-16th.

Length of Construction:
Construction will last approximately one week.

Traffic Impact:
The work will be performed during full or partial road closures.  Please note that street parking will be impacted and short term intermittent access restrictions may occur.  When construction work will be done on a particular street in the project area, the street will be posted NO PARKING prior to work on that particular street.

Pre-payment Information:
Prepayment is made to the Minneapolis Finance Department.  Pay statements are sent only by request and the taxpayer is solely responsible for obtaining said statement.  Full prepayments may be accepted only through December 31st, 2013 without interest.  Partial prepayments are not provided for.  No further notice of prepayment will be published.  Persons who wish to prepay the entire assessment lump sum without interest charges may do so by contacting the Minneapolis City Engineer's Special Assessment Office, 309 2nd Ave S, Room 209, Minneapolis, MN 55401-2268, or telephone (612)673-2401.

Meetings: 
Pre-Public Hearing:
6:30 PM, Monday, May 6, Windom South Community Center, 5843 Wentworth Ave S
Formal Public Hearing: 9:45 AM, Tuesday, May 14, Council Chambers, City Hall, 350 South 5th St, 3rd Floor

Contact:  Chris Trembath   612-919-1196

Project Updates: 

October 29th, 2013: This project is complete.  Crack sealing will take place in 2014.

October 10th, 2013: Construction began on the south-bound lanes on Monday, October 7th.  We will begin work on the north-bound lanes on Monday, October 14th.  We should be complete by October 18th.

September 11th, 2013:
 Construction is tentatively scheduled to begin the week of October 7th.

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.)  Citizens concerned with pedestrian access during construction should contact the project manager directly.
 

 

 

 

Last updated Apr. 3, 2014