35th St E Resurfacing

Project Type:
This is a paving resurfacing project. Resurfacing projects use a mill and overlay process.  This process will consist of removing a portion of the existing asphalt pavement surface and placing a new surface over the entire street. The purpose of the resurfacing program is to extend the life of a roadway by approximately 10 years.  Without this program, streets in the in the program would not see surface improvements for many years.

Project Limits:
The resurfacing project is located in south Minneapolis on 35th St E between Cedar Ave and 23rd Ave S, originally paved in 1958 which is 55 years ago; and between the railroad tracks east of Hiawatha Ave and 31st Ave S, originally paved in 1973 or 40 years ago. 

Construction Start Date:
Construction is tentatively scheduled to begin the week of May 1st, 2013.

Length of Construction:
The length of construction for this project will be approximately one week.

Traffic Impact:
The work will be performed during full or partial road closures.  Please note that street parking will be impacted and short term intermittent access restrictions may occur.  When construction work will be done on a particular street in the project area, the street will be posted NO PARKING prior to work on that particular street.

Pre-payment Information:
Prepayment is made to the Minneapolis Finance Department.  Pay statements are sent only by request and the taxpayer is solely responsible for obtaining said statement.  Full prepayments may be accepted only through December 31st, 2013 without interest.  Partial prepayments are not provided for.  No further notice of prepayment will be published.  Persons who wish to prepay the entire assessment lump sum without interest charges may do so by contacting the Minneapolis City Engineer's Special Assessment Office, 309 2nd Ave S, Room 209, Minneapolis, MN 55401-2268, or telephone (612)673-2401. 

Contact:  Chris Trembath   612-919-1196

Meetings:
Public Hearing: 6:30 PM, Wednesday, February 13, Powderhorn Recreation Center, 3400 15th Ave S
Formal Public Hearing:  9:45 AM, Tuesday, February 26, Council Chambers, City Hall, 350 South 5th St, 3rd Floor

Project Updates: 
This project is complete.  Crack sealing will take place in 2014.

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.)  Citizens concerned with pedestrian access during construction should contact the project manager directly.

 

 

 

 

 

 

 

 

 

 