Nicollet Avenue Paving - Phase 2

Project Type:
The proposed project is approximately 1 mile in length and is along Nicollet Avenue from Lake St to 40th Street.  The street was originally constructed in 1954 and asphalt overlay was done in 1977.  The proposed roadway will consist of two traffic lanes (one each way) and parking on both sides.  The project will include removal and replacement of the pavement, curb and gutter, driveways sidewalks, and storm drain inlets.

Project Limits:

The project is located in south Minneapolis on Nicollet Ave between Lake Street and 40th Street.  Phase 1, between Lake St and 36th St is now complete.  Phase 2 will be done in 2013 between 36th St and 40th St.

Construction Start Date:
The proposed project is scheduled to start May, 2012

Length of Construction:
Phase II will be completed in the 2013 construction season.

Traffic Impact:
Detour - July 11, 2013

Meetings:
March 26, 2013 Invite
March 26, 2013 Meeting Presentation

Project Update:

November 7, 2013:

There are a few things that still need to be completed (lighting, tree planting and minor clean-up), but most of the project is now complete.

October 30, 2013  
October 9, 2013  
September 26, 2013  
September 23, 2013  
September 18, 2013  
September 4, 2013  
August 21, 2013  
August 15, 2013  
August 6, 2013
July 31, 2013
July 24, 2013 
July 18, 2013
July 11, 2013
July 2, 2013
June 27, 2013
June 20, 2013
June 13, 2013
June 5, 2013
May 29, 2013
May 22, 2013   
May 15, 2013
May 8, 2013
April 30, 2013
April 25, 2013
April 23, 2013
April 19, 2013 
March 6, 2013
March 8, 2013
March 18, 2013
February 27, 2013
January 30, 2013

On-site Project Inspector:  Bob Schmidt, 651-308-3805
Project Engineer: Beverly Warmka, 612-673-3762
Project Business Liaison: Erik Hansen, 612-673-5022

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.)  Citizens concerned with pedestrian access during construction should contact the project manager directly.

Last updated Jun 4, 2014