Public Works

350 South 5th Street
RM 203 City Hall
Minneapolis, MN  55415-1390

lasalle location map

LaSalle Ave Paving

Centerpoint Energy Construction Page

Project Type:
This is a paving project that will include removal and replacement of the pavement, curb and gutter, driveway aprons and some sidewalk.

Project Limits:
This project is located in downtown Minneapolis on LaSalle Ave between 8th St S and 12th St S and will be a reconstruction project. LaSalle Ave from 12th St to Grant Ave was resurfaced in 2014.

Construction Start Date:
The reconstruction portion of the project is scheduled to start in April 2015. However, utility work started prior to the reconstruction, and much of that was completed in 2014.

Duration of Construction:
For 2015, the reconstruction project will take place starting early in the construction season and likely lasting until late summer/early fall.

Traffic Impact:
There will be lane closures on Lasalle and cross streets. It may become necessary to close Lasalle to through traffic at times. Local access will be provided and individual property owners will be contacted.

Layouts, Detours, Images:
Presentation to Property Owners 3-24-15
Utility Map
Approved Layout
City Council Committee Action Letter


Contact: Beverly Warmka 612-673-3762
Construction Contact: Tracy Lindgren 612-290-5898

Project Updates:
Update 58: 7-3-15
Update 57: 6-26-15
Update 56: 6-19-15
Update 55: 6-12-15
Update 54: 6-5-15
Update 53: 5-29-15
Update 52: 5-22-15
Update 51: 5-15-15
Update 50: 5-8-15
Update 49: 5-1-15
Update 48: 4-24-15
Update 47: 4-17-15
Update 46: 4-10-15
Update 45: 4-3-15
Update 44: 3-24-15
Update 43: 3-2-15
Update 42: 1-30-15
Update 41: 1-23-15
Update 40: 1-16-15
Update 39: 1-9-15
Update 38: 12-31-14
Update 37: 12-24-14
Update 36: 12-19-14
Update 35: 12-12-14
Update 34: 12-5-14
Update 33: 11-21-14
Update 32: 11-17-14
Update 31: 11-7-14
Update 30: 10-31-14
Update 29: 10-24-14
Update 28: 10-17-14
Update 27: 10-10-14
Update 26: 10-3-14
Update 25: 9-26-14
Update 24: 9-19-14
Update 23: 9-12-14
Update 22: 9-3-14
Update 21: 8-29-14
Update 20: 8-22-14
Update 19: 8-15-14
Update 18: 8-8-14
Update 17: 8-1-14
Update 16: 7-25-14
Update 15: 7-18-14
Update 14: 7-11-14
Update 13: 6-27-14
Update 12: 6-20-12
Update 11: 6-13-14
Update 10: 6-6-14
Update 9: 5-30-14
Update 8: 5-23-14
Update 7: 5-16-14
Update 6: 5-9-14
Update 5: 5-2-14
Update 4: 4-25-14
Update 3: 4-18-14
Update 2: 4-11-14
Update 1: 4-4-14

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly. 

Last updated Jul 2, 2015