4th loc map photos complete

4th Avenue South High Volume Resurfacing

Project Type:
This is a paving resurfacing project. Resurfacing projects use a mill and overlay process. This process will consist of removing a portion of the existing asphalt pavement surface and placing a new surface over the entire street. The purpose of the resurfacing program is to extend the life of a roadway by approximately 10 years. Without this program, streets in the in the program would not see surface improvements for many years.
This project was originally paved in 1967 and sealcoated in 1990.

Project Limits:
The 4th Avenue South project is downtown from 10th St S to 15th St E not including the intersections of 11th and 12th Sts S.

Construction Start Date:
The project is complete as of May 30, 2014.

Duration of Construction:
Two to three days.

Traffic Impact:
The work will be performed during full or partial road closures. Please note that street parking will be impacted and short term intermittent access restrictions may occur. When construction work will be done on a particular street in the project area, the street will be posted NO PARKING prior to work on that particular street.  There will be no work on the intersections of 4th Ave S and 10th, 11th, & 12th Streets.

Meetings:
Pre-Public Hearing:
2:00 PM, Wednesday, May 7, City of Lakes Building, 309 2nd Ave S, Room #203
Formal Public Hearing:
9:30 AM, Tuesday, May 13, Council Chambers, City Hall, 350 South 5th Street, 3rd Floor

Paving Construction Survey:
Once the work is complete, please let us know how we've done. To do so, please access this website and take our Project Survey: https://www.surveymonkey.com/s/4thAveS. Or, you can simply call 311 and mention this project. We'd love to hear from you!


Pre-payment Information:
Prepayment is made to the Minneapolis Finance Department. Pay statements are sent only by request and the taxpayer is solely responsible for obtaining said statement. Full prepayments may be accepted only through December 31st, 2014 without interest. Partial prepayments are not provided for. No further notice of prepayment will be published. Persons who wish to prepay the entire assessment lump sum without interest charges may do so by contacting the Minneapolis City Engineer's Special Assessment Office, 309 2nd Ave S, Room 209, Minneapolis, MN 55401-2268, or telephone (612)673-2401.

Contact: Chris Trembath 612-919-1196

Project Updates: 
May 30, 2014:  The project is complete.  Crack sealing to take place in 2015.
May 28, 2014:  Milling starts today.

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.

Last updated May 30, 2014