Public Works

350 South 5th Street
RM 203 City Hall
Minneapolis, MN  55415-1390

58 MAP AND PIC

58th St E & MN-62 Frontage Road High Volume Resurfacing

Project Type:
This is a paving resurfacing project. Resurfacing projects use a mill and overlay process. This process will consist of removing a portion of the existing asphalt pavement surface and placing a new surface over the entire street. The purpose of the resurfacing program is to extend the life of a roadway by approximately 10 years. Without this program, streets in the in the program would not see surface improvements for many years.
This project was originally paved in 1967.

Project Limits:
The 58th St/MN-62 Frontage Rd project is located in south Minneapolis.  58th from 42nd Ave S to 46th Ave S and Mn-62 from 34th Ave S to 46th Ave S.

Construction Start Date:
Stage 1 - Completed on May 6, 2014
Stage 2 - Completed on May 30, 2014

Duration of Construction:
The crosstown service road between 34th Ave S and 34th ramps to crosstown will be closed May 27-28th.

Traffic Impact:
The work will be performed during full or partial road closures. Please note that street parking will be impacted and short term intermittent access restrictions may occur. When construction work will be done on a particular street in the project area, the street will be posted NO PARKING prior to work on that particular street.

Meetings:
Pre-Public Hearing: 
6:30 PM, Wednesday, March 12, Morris Recreation Center, 5531 39th Ave S
Formal Public Hearing:
9:30 AM, Tuesday, March 18, Council Chambers, City Hall, 350 South 5th Street, 3rd Floor

Paving Construction Survey:
Once the work is complete, please let us know how we’ve done.  To do so, please access this website and take our Project Survey:  https://www.surveymonkey.com/s/58thSTE.  Or, you can simply call 311 and mention this project.  We’d love to hear from you!

Pre-payment Information:
Prepayment is made to the Minneapolis Finance Department. Pay statements are sent only by request and the taxpayer is solely responsible for obtaining said statement. Full prepayments may be accepted only through December 31st, 2014 without interest. Partial prepayments are not provided for. No further notice of prepayment will be published. Persons who wish to prepay the entire assessment lump sum without interest charges may do so by contacting the Minneapolis City Engineer's Special Assessment Office, 309 2nd Ave S, Room 209, Minneapolis, MN 55401-2268, or telephone (612)673-2401.

Contact: Chris Trembath 612-919-1196

Project Updates:
May 30, 2014: The project is complete.  Crack sealing to take place in 2015.
May 27, 2014: Stage 2 work postoned until May 28-29 due to equipment failure.
May 23, 2014: Work will continue on May 27-28. 
May 12, 2014: Everything is complete except the frontage road south of the crosstown between 34th Ave S and the freeway entrance-exit ramp.  The remainder is postponed and will be rescheduled.

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.

Last updated May 30, 2014