Public Works

350 South 5th Street
RM 203 City Hall
Minneapolis, MN  55415-1390

unpaved alley location map

Unpaved Alley

Project Type:
This is a paving project.  The alley is currently oiled dirt and will be reconstructed with concrete. 

Project Limits:
Alley south of 45th Ave N between James and Irving Avenues N.

Photos of Alley before Construction

Construction Start Date: 
September 2014

Duration of Construction:
Three weeks

Traffic Impact:
The alley will be closed during construction.

Contact: Chris Trembath 612-919-1196

Project Updates:
September 17, 2014: The alley has been poured and will be opened after the concrete is cured.  Minor landscape work to follow.
July 10, 2014:
Private utility companies are scheduling utility pole moves.

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.

Last updated Sep 17, 2014