Mid-City Industrial Reconstruction

The City of Minneapolis will be reconstructing several street segments totaling 2.2 miles in the Mid-City Industrial Neighborhood in 2019 and 2020. The project area is generally bound on the north by Interstate 35-W, on the south by E Hennepin Avenue, on the east by the city limits, and on the west by Johnson Street NE.

Mid-City Industrial Reconstruction

Project Status

CIP Status Stage 4: Construction

Project Phases

Phase I work began in 2018 and Phase II work began in 2019. See details about the two phases of this project below.

Phase I

Phase I of the Mid-City Industrial project includes segments of the following streets, which are scheduled to be finished in 2019:

  • Arthur St NE
  • Cleveland St NE
  • Broadway St NE
  • Kennedy St NE (west of Taft St NE)
  • Summer St NE
  • Taft St NE
  • Traffic St NE

All of these segments total 1.5 miles in the Mid-City Industrial neighborhood.

Mid-City Industrial Phase I Map

Phase I Presentations

Mid-City Industrial Reconstruction Pre-Assessment Meeting Presentation (March 5, 2018)

Mid-City Industrial Phase I Public Preconstruction Meeting Presentation (July 30, 2018)

Phase I Layouts

Project layouts are drafts and subject to change.

Mid-City Industrial Street Layout Segment 1
Mid-City Industrial Street Layout Segment 2
Mid-City Industrial Street Layout Segment 3

Project Contact

Petru Vizoli, Construction Engineer, 612-673-2368 or [email protected]

Raul Espinoza-Lopez, 612-673-2915 or [email protected]

Phase II

Phase II of the Mid-City Industrial project includes segments of the following streets, which are scheduled to be finished in 2020:

  • Hoover St NE
  • Kennedy St NE
  • Spring St NE
  • Godward St NE
  • Winter St NE

All of these segments total .7 miles in the Mid-City Industrial neighborhood.

See the Mid-City Industrial Phase II Meeting Presentation for more information.

Mid-City Industrial Phase II Map

Phase II Layouts

Project layouts are drafts and subject to change.

Mid-City Industrial Street Layout Segment 4
Mid-City Industrial Street Layout Segment 5

Phase II Updates

Week of May 6, 2019

  • All the storm sewer work on Hoover St – north of Broadway St has been completed.
  • the utilities crew has completed the sanitary sewer manhole replacement at the same location. Hence all the underground utility work at this location has been completed.
  • The subgrade and the base on Hoover St – north of Broadway has been prepared, and the road is ready to be paved.
  • The sanitary bypass on Hoover St, Spring St and Godward St had all its pipe fused this week and crossings at major intersections along this stretch have been made. Hence, the sanitary bypass has its pumps and pipe in place and is ready to be tested.
  • CenterPoint/ Michels – gas main line installation on progress on Hoover St NE north of Spring ST NE

Proposed work for week of May 13, 2019

  • The pumps for the sanitary bypass are set to be tested on Monday, 5/13.
  • Sanitary sewer work will start on Spring St on Monday, 5/13.
  • The subcontractor for concrete paving will be on site starting Tuesday, 5/14 ready for concrete work on Hoover St – north of Broadway St. Curb and gutter is planned for Tuesday, driveway aprons and tie-ins for Wednesday, and paving the roadway for rest of the week is what is planned.

If you have any question or concern please call Ayalew Getaneh  612-499-7557 or  e-mail  [email protected]

Week of April 29, 2019

Our crews:

  • Removed concrete pavement, curb and gutter, and driveways on Hoover north of Broadway completed
  • Started removing concrete pavement on Hoover between Winter and Kennedy, and also down Spring
  • Installing storm sewer on Hoover north of Broadway
  • Roadway subbase preparation started

Centerpoint Energy crews continued installing gas main; and will be starting individual services next week

Mid City Industrial Photo 4-29-19

Week of April 22, 2019

Our crews:

  • milled the 2” bituminous layer off the roadway on Hoover between Hennepin and Broadway.
  • began removing concrete pavement on Hoover north of Broadway.

CenterPoint Energy crews installing gas main.

Mid City Industrial Photo 4-22-19

Project Contact

Ayalew Getaneh, Project Manager, City of Minneapolis, 612-673-6055 or [email protected]

Gregg Johnson, Construction Engineer, Rani Engineering, 612-455-3322 ext. 138 or [email protected]

Craig Larson, Chief Field Inspector, Stantec, [email protected]

Project Documents

All Project Layouts

Project layouts are drafts and subject to change.

Mid-City Industrial Street Layout Segment 1
Mid-City Industrial Street Layout Segment 2
Mid-City Industrial Street Layout Segment 3
Mid-City Industrial Street Layout Segment 4
Mid-City Industrial Street Layout Segment 5

Contact

Phase 1 - Petru Vizoli, Construction Engineer, 612-673-2368 or [email protected]

Phase 2 - Ayalew Getaneh, Project Manager, City of Minneapolis, 612-673-6055 or [email protected]

 

Last updated May 17, 2019

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

Minneapolis 311       ©1997-2019 City of Minneapolis, MN

CONNECT

311 call center

311 TTY relay service

City of Minneapolis Facebook City of Minneapolis Twitter City of Minneapolis YouTube ChaNNEL Minneapolis 311 Watch Minneapolis City Council TV City of Minneapolis LinkedIn

Minneapolis, City of Lakes logo