Industrial Boulevard Shared Use Trail

Industrial Blvd Shared Use Trail Map

Project Status

Project Status: Construction

Project Background

Public Works has identified a shared use trail connecting planned shared use trails on Broadway St NE and Industrial Blvd.  The objective of this project is to connect the planned improvements for a continuous facility from Ridgway Parkway to Stinson Blvd NE.

Project Scope

The proposed project consists of a new off-street multi-use trail on the west side of Industrial Boulevard extending from the south side of I-35W to Broadway Street Northeast. The elements proposed to be included as part of the project includes a new curb-level multi-use trail, ADA compliant curb ramps, curb/gutter, and utility improvements. The project will also include pedestrian scale parkway lighting, planted trees within the boulevard where feasible, signage, and pavement markings. Public Works is partnering with Minneapolis Park and Recreation Board (Park Board) to fund the project, with construction anticipated in 2019.

The project area is approximately 0.12 miles in length and currently consists of three southbound travel lanes, a center median, two northbound travel lanes, and no sidewalk within a 100-ft right-of-way. The adjacent land uses to the west side of the project area include a hotel and office space with driveways facing Industrial Boulevard.

Project Details

The project layout was approved by the Transportation and Public Works Committee on November 27, 2018. The project is now in the design phase, and anticipated to be built during the 2019 construction season.

Approved Layout

Construction Start Date

Tentative construction start date is September 2019.

Duration of Construction

It is anticipated that this project will be substantially complete during this construction season.  Trees will be planted in the spring of 2020.

Traffic Impact

For the most part, southbound Industrial Boulevard will be a single lane.  There will be a closure with a detour in place for a weekend in September, to install storm sewer.  A detour will be in place.

There will be times during construction that northbound Industrial Blvd will be a single lane.  This is to make pedestrian ramp upgrades at the Godward St SE intersection.

Industrial Blvd Project Detour Routes Map 8-23-19

Contact

If you would like to learn more about the proposed reconstruction, request additional information, or share your ideas please visit the project website or contact the project team using the contact information provided below. 

Tracy Lindgren, Construction Engineer, Minneapolis Public Works
612-290-5898 or [email protected]

Bill Fellows, Project Engineer, Minneapolis Public Works
612-673-5661 or [email protected]

Last updated Aug 23, 2019

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

Minneapolis 311       ©1997-2019 City of Minneapolis, MN

CONNECT

311 call center

311 TTY relay service

City of Minneapolis Facebook City of Minneapolis Twitter City of Minneapolis YouTube ChaNNEL Minneapolis 311 Watch Minneapolis City Council TV City of Minneapolis LinkedIn

Minneapolis, City of Lakes logo