Alley Renovation Program

Alley renovation uses an asphalt overlay to improve the quality of the pavement surface. These projects are necessary to provide high quality alley surfaces and maintain positive alley drainage. If this work is not done, it is likely that more expensive and work intensive reconstruction will need to be performed in the future.

Project Status


CIP Status Stage 2: Design

Project Details

Duration of Construction:
The renovation work on an alley may extend for up to three days. These days are generally not consecutive. On the first day, if there is an existing asphalt surface, the top 2” is milled off. This is done by using a machine that grinds off the top layer of pavement. If the alley has a concrete surface, this step is omitted. The surface is then thoroughly cleaned and swept. On the second work day, a new asphalt surface is placed over the existing pavement.

During the following calendar year, the alley will be seal coated. Seal coating provides additional protection to the alley, extending the service life of the asphalt surface. It involves placing asphalt emulsion on the pavement and spreading chips, such as granite, over the emulsion. The surface is rolled with specialized compaction equipment. After a few days, the alley is swept to pick up any excess chips.

Impact to Residents:
The alley will be closed to traffic during a portion of the work. If milling is required, partial access will be permitted to the alley. The mill will be a moving obstruction. It is recommended that you move your vehicle if you know that you will need it. When asphalt is placed, there will be equipment and a required cooling time. This will impact garage and parking access along the alley for a number of hours, and residents will need to move their cars in advance of the asphalt work.

Residents will be notified in advance of the work. This will be done through hand delivering letters to residents along the alley. This letter will include the date of the work. The City will also use its automated calling system. There will also be coordination with the Sanitation Department. The work will be scheduled to minimize conflict between the resurfacing work and with weekly sanitation pick-ups. Residents will not need to take any action in regards to sanitation pick-ups.

2019 Alley Locations

Project Limits:
2019 locations will include alleys throughout the city.

Construction Start Date:
Construction will be done during the 2019 construction season.

2018 Alley Locations

Project Limits:
Alleys are located throughout the city. Please see the Alley Resurfacing Book for locations.

Construction Start Date:
Construction will be done during the 2018 construction season. See the Alley Resurfacing Schedule.

2017 Alley Locations

Project Limits:
Alleys are located throughout the city. Please see the Alley Resurfacing Book for locations.

Construction Start Date:
Construction will be done during the 2017 construction season. See the Alley Resurfacing Schedule.

2017-PV006-Alleys-webmap.gif

2016 Alley Locations

Project Limits:
Alleys are located throughout the City. Please see detailed map for locations.

Construction Start Date:
Construction will be done during the 2016 construction season. See the 2016 Tentative Alley Renovation Schedule.

Alley Renovation Webmap 2016

Contact

Gary Long, Jr., [email protected] or 612-673-5591

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.

Last updated Feb 22, 2019

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

Salary Compliance Notice:
State statute 471.701; Notice of Salary Compliance, requires that the City post for not less than 90 days
the job title of the three highest paid employees along with their base salary. For 2018 these were:
1. City Attorney, $186,490
2. Assistant City Coordinator Convention Center, $183,600
3. Director Public Works, $181,191