North Loop Paving & Pedestrian Enhancements

The proposed project will reconstruct portions of 3rd St N, 5th Ave N, 7th Ave N, 8th Ave N and 9th Ave N adding up to approximately 0.8 miles of street within the North Loop neighborhood. The project is a reconstruction project involving the entire right-of-way and will include new sidewalks, ramps, pavement, curb and gutter, and utility improvements. The project will also include signal improvements, new signage, and new pavement markings, as needed.

Construction will begin in April 2019 and complete in Spring 2020.

 Sign up for email updates for North Loop Paving & Pedestrian Enhancements:

Email Updates
To sign up for updates or to access your subscriber preferences, please enter your contact information below.
 

 NorthLoop Paving Project

Project Status

CIP Status Stage 2: Designing

 

Final Preliminary Concept
The project team has developed a final recommended concept that will be brought to City Council Transportation & Public Works Committee on March 27th for consideration for layout approval.

Final Preliminary Concept
The project team has developed an updated preliminary concept, which takes into consideration input from the previous meetings with various stakeholders. The concept will be brought to the City's Heritage Preservation Commission on December 12th 2017 for further feedback. An final project planning meeting will be held on December 18th 2017 to discuss this  concept. Feedback from these two meetings will be considered in developing the final staff recommended concept to be considered for City Council approval in early 2018.

Meeting notifications were mailed to property owners on December 1st, 2017

Project Details

Project Location

3rd St N (5th Ave N - 10th Ave N), 5th Ave N (5th St N - Washington Ave N), 7th Ave N (4th St N - Washington Ave N), 8th Ave N (3rd St N - Washington Ave N), 9th Ave N (3rd St N - Washington Ave N)

Construction Date

This project is scheduled to be constructed in 2019.

Construction Duration

TBD.

See also the related North Loop Pedestrian Improvement project.

Project Materials

Open House 1 & 2 Notifications

Open House 1 Boards - Introduction

Open House 2 Boards - Preliminary Design

Open House 2 - Preliminary Layouts

Updated Preliminary Concept - December 18th, 2017

Meeting 3 Slides - December 18th, 2017

Street Materials Diagram - December 18th, 2017

FINAL RECOMMENDED CONCEPT - March 15th, 2018

Pre-Assessment Presentation - November 13, 2018

Meetings

The City of Minneapolis Department of Public Works will be holding a series of public meetings to gather feedback regarding the proposed project. The first two public meetings will be held at the dates below, with a third final public meeting scheduled tentatively for November 2017.
 

Public Meeting #1, Introductory Open House:

Minneapolis Central Library, Doty Board Room-N280
300 Nicollet Mall, Minneapolis, MN 55401
Monday, July 24th, 2017 
Open House Hours, 5:30 p.m. – 7:00 p.m.

 

Public Meeting #2, Preliminary Concepts Open House:

Minneapolis Central Library, Doty Board Room-N280
300 Nicollet Mall, Minneapolis, MN 55401
Tuesday, August 29th, 2017 

Open House Hours, 5:30 p.m. - 7:00 p.m.

 

Public Meeting #3, Final Preliminary Concept:

Minneapolis Central Library, Doty Board Room-N280
300 Nicollet Mall, Minneapolis, MN 55401
Monday, December 18th, 2017 

Project Presentation at 5:30 p.m. followed by Q&A

 

Heritage Preservation Commission, Introductory Presentation
Minneapolis City Hall, Room 317
350 South 5th Street, Minneapolis, MN 55415
Tuesday, December 12th, 2017 

Meeting begins at 4:30pm. Item location on the agenda TBD.

 

 Existing Site Photos:
North Loop -1     North Loop -2     North Loop 3

Schedule

Planning & Public Engagement
Community engagement was conducted, August 2017 - March 2018.

Engineering Design
Engineering/Final Design will take place in 2018

Construction
Construction is scheduled for 2019

Project Updates

3/8/19 Construction will begin in April 2019 and complete in Spring 2020.

3/15/18 A final recommended project layout has been uploaded to the website.

12/18/17 The final project planning meeting took place on 12/18/17. Slides from the meeting are posted on the project website.

12/12/17 The project was presented to the Minneapolis Heritage Preservation Commission as an informational item.

12/1/17 The final project planning meeting will take place on 12/18/17 at 5:30 pm at Minneapolis Central Library

12/1/17 A final preliminary concept has been developed and has been uploaded to the website

8/29/17 The second project open house will be held on 8/29 from 5:30pm - 7:00pm at Minneapolis Central Library

8/28/17 The introductory project survey has been closed

8/2/17 Project staff attended a Minneapolis Advisory Committee on People with Disabilities (MACOPD) meeting to introduce the project

7/24/17 The introductory open house was held at Minneapolis Central Library

7/26/17 Project staff attended a North Loop Neighborhood Association meeting to introduce the project

7/20/17 Project staff attended the City's Pedestrian Advisory Committee to introduce the project

7/18/17 Project staff attended a 2020 Partners meeting to introduce the project

7/18/17 Project staff attend the City's Bicycle Advisory Committee to introduce the project

7/11/17 Meeting notifications for the upcoming open houses have been sent to property addresses in the area.
 

Project Contacts

Forrest Hardy, Project Planner, [email protected]  

Adam Hayow, Project Engineer, [email protected]

 

Last updated Mar 11, 2019

QUICK LINKS

Home

Contact us

Email updates

Find a service

About this site

For employees

Accessibility:
For reasonable accommodations or alternative formats, contact 311.
People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000.
TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-637-2800, Hadii aad Caawimaad u baahantahay 612-673-3500. 

Salary Compliance Notice:
State statute 471.701; Notice of Salary Compliance, requires that the City post for not less than 90 days
the job title of the three highest paid employees along with their base salary. For 2018 these were:
1. City Attorney, $186,490
2. Assistant City Coordinator Convention Center, $183,600
3. Director Public Works, $181,191