Minneapolis Plumbing and RPZ Permit
Fee Schedule
Effective April 4, 2005
TYPE OF WORK
|
FEE
|
Minimum Fee - Residential / Commercial
|
$60.00 (Includes $0.50 State Surcharge)
|
Full Fixture - All Occupancies
|
$29.25
|
Fixture Set Only - All Occupancies
|
$29.25
|
Waste and Vent Only - All Occupancies
|
$29.25
|
Rainwater Leader, for 10 stories or fraction thereof
|
$29.25
|
Replacing or Extending water distribution piping, each 100 lineal feet or fraction thereof
|
$29.25
|
Alterations - each $500 or fraction thereof
|
$29.25
|
RPZ - All Occupancies
(Minimum Fee does not apply)
(Includes $0.50 State Surcharge)
|
$29.75
|
MN State Surcharge fee of $0.50 should be added to the total permit fee (except minimum as shown).
Non-Heating Gas Burner Permit Fees*
INPUT (BTU / HR)
|
FEE
|
Minimum Fee - Residential / Commercial
|
$60.00 (Includes $0.50 State Surcharge)
|
Not Exceeding 199,999
|
$52.00
|
200,000 - 399,999
|
$103.75
|
400,000 - 999,999
|
$206.25
|
1,000,000 - 2,499,000
|
$295.00
|
2,500,000 and over
|
$737.75
|
Alterations to existing system:
|
|
$1.00 - $50,000
|
1.58% of the total cost of the work
|
$50,001 and over
|
$790.00 plus 1.05% of value of work over $50,000
|
Gas Alteration Only
|
1.58% of value or minimum fee, whichever is greater
|
Transitory Projects, Events, or Special Inspections
|
$57.25 per hour or fraction thereof (minimum fee of $114.50)
|